建筑网校 | 选课中心 | 网校名师 | 建筑文苑 | 政策法规 | 专业资料 | 建筑实务 | 专题 | 邮箱 | 论坛 | 建筑书店 | 学习卡 | 首页 Zhengbao Education | Architecture Online School | Elective Center | Online School Master | Architecture Garden | Policies and Regulations | Professional Information | Construction Practice | Special Topics | Email | Forum | Architecture Bookstore | Learning Card | Home

Construction Engineering Education Network > Policies and Regulations > Administrative Regulations > Text

Regulations on safety management of more dangerous sub-projects

2018-03-21 18:46 Ministry of Housing and Urban-Rural Development [Large, Medium and Small] [Print] [I want to correct]

Order of the Ministry of Housing and Urban-Rural Development of the People's Republic of China No. 37

The "Regulations on the Safety Management of Major Dangerous Sub-projects" have been deliberated and approved at the 37th Executive Meeting of the Ministry on February 12, 2018, and are hereby promulgated for implementation on June 1, 2018.

Ministry of Housing and Urban-Rural Development

Wang Menghui

March 8, 2018

Regulations on safety management of more dangerous sub-projects

Chapter I General Provisions

Article 1 In order to strengthen the safety management of some of the more dangerous sub-projects in housing construction and municipal infrastructure projects, and effectively prevent production safety accidents, according to the “Building Law of the People ’s Republic of China” These regulations are formulated in accordance with laws and regulations such as the Regulations on the Management of Project Safety in Production.

Article 2. These regulations apply to the safety management of sub-projects that are more dangerous in building construction and municipal infrastructure projects.

Article 3 The more dangerous sub-projects referred to in these regulations (hereinafter referred to as "dangerous major projects") refer to the construction of houses and municipal infrastructure projects, which may easily lead to death or injury to persons or cause major Sub-projects of economic loss.

Dangerous projects and the scope of dangerous projects exceeding a certain scale shall be formulated by the State Council's housing urban and rural construction department.

Provincial housing and urban-rural construction authorities may combine the actual situation in the region to supplement the scope of major hazardous projects in the region.

Article 4 The department in charge of housing and urban-rural construction of the State Council is responsible for the guidance and supervision of the safety management of critical national projects across the country.

The competent departments of housing, urban and rural construction of local people's governments at or above the county level are responsible for the safety supervision and management of dangerous projects within their own administrative areas.

Chapter II Early Guarantee

Article 5 The construction unit shall provide truthful, accurate and complete information on engineering geology, hydrogeology and the surrounding environment of the project.

Article 6 The survey unit shall, based on the actual conditions of the project and environmental data surrounding the project, state in the survey documents the engineering risks that may be caused by geological conditions.

The design unit shall indicate in the design documents the key parts and links involved in the critical project, put forward suggestions to ensure the safety of the surrounding environment of the project and the safety of the project construction, and carry out special design when necessary.

Article 7 The construction unit shall organize survey, design and other units to list the list of dangerous projects in the bidding documents for construction, and require the construction unit to complete and complete the list of dangerous projects and specify corresponding safety management measures when bidding.

Article 8 The construction unit shall promptly pay the technical measures for the construction of dangerous projects and the corresponding measures for safety protection and civilized construction measures in accordance with the construction contract to ensure the safety of the construction of dangerous projects.

Article 9 When applying for safety supervision formalities, the construction unit shall submit information such as the list of dangerous projects and its safety management measures.

Chapter III Special Construction Scheme

Article 10 The construction unit shall organize engineering and technical personnel to prepare a special construction plan before the construction of a critical project.

For the implementation of general contracting, the special construction plan shall be prepared by the general contracting unit. In the case of subcontracting of dangerous projects, special construction schemes may be prepared by relevant professional subcontracting units.

Article 11 The special construction plan shall be reviewed and signed by the technical person in charge of the construction unit and affixed with the official seal of the unit, and shall be implemented after being examined and signed by the chief engineer and affixed with the practice seal.

Where a dangerous project is subcontracted and a special construction plan is prepared by the subcontracting unit, the special construction plan shall be jointly reviewed and signed by the technical contractor of the general contractor and the technical contractor of the subcontracting unit and shall be affixed with the official seal of the unit.

Article 12 For dangerous large projects exceeding a certain scale, the construction unit shall organize an expert demonstration to demonstrate the special construction plan. In the case of general construction contracting, an expert demonstration meeting shall be organized by the general construction contracting unit. Experts justified that the special construction plan should pass the review of the construction unit and the review of the chief engineer.

Experts shall be selected from an expert database established by the competent department of housing urban and rural construction of the local people's government, which shall meet the professional requirements and shall be no less than five. Personnel who have an interest in this project shall not participate in the expert demonstrative meeting as an expert.

Article 13 After the expert argumentation meeting, an argumentation report shall be formed, and unanimous opinions on the approval, modification, or rejection of the special construction plan shall be proposed. Experts are responsible for the demonstration report and sign for confirmation.

If the special construction plan needs to be approved after being demonstrated, the construction unit shall re-perform the procedures in Article 11 of these regulations after it has been revised and improved according to the demonstration report.

If the special construction plan fails to pass the argument, the construction unit shall reorganize the expert argument in accordance with the requirements of this regulation after modification.

Chapter IV Site Safety Management

Article 14 The construction unit shall announce the name of the dangerous project, the construction time and the specific responsible personnel at a prominent position on the construction site, and set up safety warning signs in the dangerous area.

Article 15 Prior to the implementation of the special construction plan, the compiler or project technical person in charge shall submit the plan to the construction site management personnel.

The construction site management personnel shall provide safety technical information to the operating personnel, and shall be signed and confirmed by both parties and the project full-time safety production management personnel.

Article 16 The construction unit shall organize construction strictly in accordance with the special construction plan, and shall not modify the special construction plan without authorization.

If it is really necessary to adjust due to planning adjustments, design changes, etc., the revised special construction plan shall be re-examined and demonstrated in accordance with these regulations. Where funds or construction period adjustments are involved, the construction unit shall make adjustments in accordance with the agreement.

Article 17 The construction unit shall register the construction operators of dangerous major projects, and the person in charge of the project shall perform his duties at the construction site.

The full-time safety production management personnel of the project shall conduct on-site supervision of the implementation of the special construction plan. Those who fail to implement the special construction plan shall require immediate rectification and report to the project leader in a timely manner. The project leader shall organize the rectification within a time limit.

The construction unit shall carry out construction monitoring and safety inspections of the dangerous major projects in accordance with regulations, and shall discover the emergency situations that endanger personal safety, and shall immediately organize the workers to evacuate the dangerous area.

Article 18 The supervision unit shall compile the detailed implementation rules of supervision in conjunction with the special construction plan of the major dangerous project, and carry out a special inspection and inspection of the major dangerous project construction.

Article 19 If the supervision unit finds that the construction unit has not carried out the construction in accordance with the special construction plan, it shall require it to make rectification; if the circumstances are serious, it shall require it to suspend construction and report to the construction unit in a timely manner. If the construction unit refuses to rectify or suspend construction, the supervision unit shall promptly report to the construction unit and the competent department of housing urban and rural construction where the project is located.

Article 20 For dangerous major projects that require third-party monitoring in accordance with regulations, the construction unit shall entrust units with corresponding survey qualifications to carry out monitoring.

The monitoring unit shall prepare a monitoring plan. The monitoring plan shall be signed by the person in charge of the technical unit of the monitoring unit and affixed with the official seal of the unit, and it shall be implemented after being submitted to the supervision unit.

The monitoring unit shall carry out monitoring in accordance with the monitoring plan, report the monitoring results to the construction unit in a timely manner, and be responsible for the monitoring results; when an abnormality is found, report to the construction, design, construction, and supervision unit in a timely manner, and the construction unit shall immediately organize the relevant unit to take disposal measures .

Article 21 The construction unit and the supervision unit shall organize relevant personnel to carry out inspection and acceptance of dangerous and major projects that need to be inspected and accepted in accordance with regulations. Those who pass the inspection and acceptance shall be signed and confirmed by the person in charge of the project technical director and chief engineer of the construction unit before entering the next process.

After the acceptance of a critical project, the construction unit shall set up an acceptance sign at an obvious location on the construction site to publicize the acceptance time and responsible personnel.

Article 22 When a dangerous situation or accident occurs in a major project, the construction unit shall immediately take emergency measures and report it to the competent department of housing urban and rural construction where the project is located. Construction, survey, design, supervision and other units shall cooperate with the construction unit in carrying out emergency rescue work.

Article 23 After the emergency rescue of a major project is over, the construction unit shall organize survey, design, construction, supervision and other units to formulate a project restoration plan and conduct a post-evaluation of the emergency rescue work.

Article 24 Construction and supervision units shall establish safety management archives of major and dangerous projects.

The construction unit shall incorporate the special construction plan and related materials such as review, expert demonstration, delivery, site inspection, acceptance and rectification, etc.

The supervision unit shall incorporate relevant information such as the implementation details of the supervision, the review of the special construction plan, the special inspection inspection, acceptance and rectification, etc.

Chapter V Supervision and Management

Article 25 The competent department of housing and urban-rural construction of local people's governments at or above the district level shall establish an expert bank, formulate an expert bank management system, establish an expert integrity file, and make it public to the public and accept social supervision.

Article 26 The competent department of housing urban and rural construction of the local people's government at or above the county level or the construction safety supervision institution affiliated to it shall conduct random inspections of major hazardous projects in accordance with the supervision work plan.

The competent department of housing urban and rural construction of the local people's government at or above the county level or its subordinate construction safety supervision agency may purchase technical services from the government to hire units and personnel with professional and technical capabilities to carry out inspections of major and dangerous projects. The expenses required shall be applied to the finance department at the same level. Be protected.

Article 27 The competent department of housing and urban-rural construction of the local people's government at or above the county level or the construction safety supervision organization affiliated with it shall, when it finds that there are hidden safety hazards in major projects during the supervision and random inspection, shall order the construction unit to make rectifications; or remove major hidden safety hazards before or eliminate If the safety cannot be guaranteed during the process, the operator shall be ordered to withdraw from the dangerous area or temporarily suspend construction; for the act that should be given administrative punishment according to law, an administrative punishment decision shall be made according to law.

Article 28 The competent department of housing urban and rural construction of the local people's government at or above the county level shall incorporate the punishment information of units and individuals into the bad credit records of construction safety.

Chapter VI Legal Liability

Article 29 A construction unit that commits one of the following acts shall be ordered to make corrections within a time limit and imposed a fine ranging from 10,000 yuan to 30,000 yuan; the person in charge directly responsible and other directly responsible persons shall be punished from 1,000 yuan to 5,000 yuan fine:

(1) Failure to provide information about the surrounding environment of the project in accordance with these regulations;

(2) Failure to list dangerous and hazardous projects in the bidding documents in accordance with these regulations;

(3) Failure to pay in time the technical measures for the construction of the critical project or the corresponding measures for safety and civilized construction measures in accordance with the construction contract;

(4) Failure to entrust a unit with corresponding survey qualifications to carry out third-party monitoring in accordance with these regulations;

(5) Failure to take measures to deal with abnormal situations reported by third-party monitoring units.

Article 30 If the survey unit fails to explain the engineering risks that may be caused by geological conditions in the survey documents, it shall be ordered to make corrections within a time limit, and the unit shall be punished in accordance with the "Regulations on the Management of Construction Project Safety in Production"; the directly responsible supervisors and other directly responsible personnel Impose a fine of 1,000 yuan to 5,000 yuan.

Article 31 If the design unit fails to indicate in the design documents the key parts and links involved in the major project, and does not put forward opinions to ensure the safety of the surrounding environment of the project and the safety of the construction of the project, it shall be ordered to make corrections within a time limit, and shall be imposed for more than 10,000 yuan3 Fines up to 10,000 yuan; directly responsible persons in charge and other directly responsible persons shall be fined 1,000 yuan to 5,000 yuan.

Article 32 If a construction unit fails to compile and review a special construction plan for a major project in accordance with these regulations, the unit shall be punished in accordance with the “Regulations on the Management of Construction Project Safety in Production” and temporarily withheld a production safety license for 30 days; Supervisors and other directly responsible persons shall be fined from 1,000 yuan to 5,000 yuan.

Article 33 If a construction unit commits one of the following acts, the unit and relevant responsible personnel shall be punished in accordance with the “Safety Production Law of the People ’s Republic of China” and the “Regulations on the Management of Construction Project Safety Production”:

(1) Failure to submit the scheme and safety technology to the construction site managers and operators;

(2) failing to announce dangerous projects at a prominent location on the construction site and setting up safety warning signs in dangerous areas;

(3) The full-time safety production management personnel of the project failed to conduct on-site supervision of the implementation of the special construction plan.

Article 34 If a construction unit commits one of the following acts, it shall be ordered to make corrections within a time limit, and a fine of 10,000 yuan to 30,000 yuan shall be imposed and the production safety license shall be temporarily suspended for 30 days; the person in charge directly responsible and other direct responsibilities Persons are fined from 1,000 yuan to 5,000 yuan:

(1) Failure to carry out expert demonstration of the special construction plan of a major hazardous project exceeding a certain scale;

(2) failing to modify the special construction plan for critical large-scale projects exceeding a certain size according to the expert demonstration report, or failing to reorganize the expert demonstration in accordance with these regulations;

(3) Failure to organize construction strictly in accordance with the special construction plan, or modify the special construction plan without authorization.

Article 35 If a construction unit commits one of the following acts, it shall be ordered to make corrections within a time limit, and a fine of 10,000 yuan to 30,000 yuan shall be imposed; the person in charge directly responsible and other directly responsible persons shall be punished by 1,000 yuan to 5,000 yuan. fine:

(1) The person in charge of the project fails to perform his duties on site or organize rectification within a time limit in accordance with these regulations;

(2) The construction unit fails to conduct construction monitoring and safety inspections in accordance with these regulations;

(3) Failure to organize acceptance of dangerous major projects in accordance with these regulations;

(4) Failing to take emergency measures when a dangerous situation or accident occurs;

(5) Failure to establish a safety management file for major projects in accordance with these regulations.

Article 36 If a supervision unit commits one of the following acts, the unit shall be punished in accordance with the “Safety Production Law of the People ’s Republic of China” and the “Regulations on the Administration of Work Safety in Construction Engineering”; the person in charge directly responsible and other persons directly responsible shall be punished 1,000 yuan Fines above 5,000 yuan:

(1) The supervisory engineer fails to review the special construction plan of the major dangerous project in accordance with these regulations;

(2) It is found that the construction unit has not implemented according to the special construction plan, and has not requested its rectification or suspension of work;

(3) When the construction unit refuses to rectify or suspend construction, it fails to report to the construction unit and the competent department of housing urban and rural construction where the project is located.

Article 37 If a supervision unit commits one of the following acts, it shall be ordered to make corrections within a time limit and be fined from 10,000 yuan to 30,000 yuan; the person in charge directly responsible and other directly responsible persons shall be imposed from 1,000 yuan to 5000 yuan fine:

(1) Failure to compile detailed rules for supervision implementation according to these regulations;

(2) Failing to carry out special inspection and inspection on the construction of dangerous major projects;

(3) Failure to participate in the organization of acceptance of critical major projects in accordance with these regulations;

(4) Failure to establish a safety management file for major projects in accordance with these regulations.

Article 38 If a monitoring unit commits one of the following acts, it shall be ordered to make corrections within a time limit and be fined from 10,000 yuan to 30,000 yuan; the person in charge directly responsible and other directly responsible persons shall be imposed from 1,000 yuan to 5,000 yuan fine:

(1) Failing to obtain corresponding survey qualifications to engage in third-party monitoring;

(2) Failure to prepare a monitoring plan in accordance with these regulations;

(3) Failure to carry out monitoring in accordance with the monitoring plan;

(4) The abnormality was not reported in time.

Article 39 If the staff of the local urban and rural construction department of the local people's government at or above the county level or the construction safety supervision organization affiliated with it fails to perform their duties of safety supervision and management of dangerous major projects according to law, they shall be punished according to relevant regulations.

Chapter VII Supplementary Provisions

Article 40 These Provisions shall become effective on June 1, 2018.

[ I want to correct ] Editor in charge: lala
Collection sharing: Forum
share to:
Next:
related news
  • Featured Class
    4 shifts + 2-3 sets of true-to-life simulation questions to improve learning results
  • Excellent class
    4 major shifts + 2-3 sets of true simulation questions + 1 set of pre-test questions
  • Experimental class
    3 sets of real simulation questions + 2 sets of pre-test questions + exam pass
  • Custom Class
    3 sets of simulation questions + 3 sets of prediction questions
  • Mobile class
    Lessons are taught in units of knowledge points,
    Strengthen the key points, difficult points, and test points
Copyright Notice

1. All works marked "Source: Construction Engineering Education Network" on this website, the copyright belongs to Construction Engineering Education Network, and may not be reproduced, linked, reposted or used in other ways without authorization from this website; , Should be used within the scope of authorization, and must be marked "Source: Construction Engineering Education Network". Anyone who violates the above statement will be held legally responsible.
2. Some materials on this website are collected and reprinted online. Every effort is made to indicate the author and source. For works on this website that involve copyright and other issues, the author is requested to contact this website, and this website will deal with it as soon as possible after verification.
A work reproduced on this website does not imply endorsement of the views or authenticity of the work. If reprinted by other media, websites or individuals, please contact the copyright owner and bear legal responsibility.
3. This website welcomes contributions.